The Project Management Institute (PMI) offers a variety of certifications for professionals in the project management industry, including the Certified Associate in Project Management (CAPM) certification. The CAPM certification is designed for individuals who are new to project management and looking to establish their foundational knowledge and skills. It is also a great option for those who do not yet meet the requirements for the more advanced Project Management Professional (PMP) certification.

CAPM – Certified Associate in Project Management (PMI-100)

CAPM exam is part of the new PMI Certified Associate in Project Management certification. This is an entry-level certification in project management. This exam measures candidates knowledge in the principles and terminology of A Guide to the Project Management Body of Knowledge (PMBOK Guide).

 

NO.112 Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

 
 
 
 

NO.113 Due to today’s competitive global market, organizations require more than technical project management skills.
Which of the following skills can support long-range strategic objectives that contribute to the bottom line?

 
 
 
 

NO.114 A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable.
This could have been avoided if the project team had implemented:

 
 
 
 

NO.115 Which input to the Plan Risk Management process provides information on high-level risks?

 
 
 
 

NO.116 How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

 
 
 
 

NO.117 A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks.
Given these three estimates, what is the expected duration of the activity?

 
 
 
 

NO.118 What is the main benefit of the lessons learned register?

 
 
 
 

NO.119 Given the following information:
* Activity A takes one week.
* Activity B takes three weeks.
* Activity C takes two weeks.
* Activity D takes five weeks.
* Activity A starts at the same time as Activity B.
* Activity C follows Activity B and Activity A.
* Activity D follows Activity C.
How long will it take to complete the project?

 
 
 
 

NO.120 At which stage of team development do members begin to work together, adjust work habits, and trust each other?

 
 
 
 

NO.121 At what stages of a project should the Identify Stakeholders process be performed?

 
 
 
 

NO.122 When does the project team determine which dependencies are discretionary?

 
 
 
 

NO.123 Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

 
 
 
 

NO.124 A key benefit of the Manage Communications process is that it enables:

 
 
 
 

NO.125 Which of the following is an output from Control Scope?

 
 
 
 

NO.126 Which characteristic is unique to project work and does not apply to operational work?

 
 
 
 

NO.127 Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

 
 
 
 

NO.128 A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

 
 
 
 

CAPM Actual Questions Answers PDF 100% Cover Real Exam Questions: https://www.dumpsreview.com/CAPM-exam-dumps-review.html

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Related Posts

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below